Monday, March 10, 2014

Dye's Valley Infrastructure Renovation - Week 1

It has been a successful first week of closure on Dye's Valley as the infrastructure renovation has officially started.
 Demolition of the existing greens complexes and bulkheads took priority when the course closed.
 Bulkhead demolition. 
 Bulkhead reconstruction. 
Bulkhead pylons being set.
Bulkhead installation nears completion on #11.
 Excavation of the existing greens bowl at #4.  
 3-D Mapping and GPS data is used to ensure the greens are returned to the same shape and design. 
 Completed sub-grade of #4.
Drainage and gravel layer being installed on #4.